1. The site for selecting and installing the tape machine must be on a relatively flat and hardened ground, as a good environment is required for the operation of the tape machine. It cannot be said that the ground is bumpy or uneven, and the operation of various parts is not coordinated, resulting in the production of unqualified products! All of these need to be considered.
2. Machine assembly, the components of the tape machine are usually separated. Before installation, after selecting a suitable site, place the front and rear middle frames on a horizontal ground to maintain a uniform horizontal line! To maintain stable homework.
3. After installation, perform pre-treatment on various parts of the machine, including chains, sprockets, bearings, reducers, and adding lubricating oil or grease
4. After lubrication treatment, adjust the main components to ensure smooth rotation without any blockage.
5. After the installation of each part is completed, turn on the power and conduct a test run! No installation materials are required during the testing process, bare testing is conducted! Observe the operation of each component! Discover abnormalities and perform power outage processing
6. For safety reasons, it is necessary to disconnect the power supply of the tape machine when it is not in operation